Skip to main content
HGCRA Pro Forma

Interim Payment Application Form

A blank, ready-to-complete interim payment application. Set out the valuation, apply retention, state the net sum due, and record the HGCRA payment and pay-less dates so your application stands as the notified sum.

1 · Application details

Project name
Full project name as stated in the subcontract
Subcontract / contract reference
Exactly as it appears in the subcontract
Application number
Sequential — e.g. AFP-014
Application / valuation date
DD/MM/YYYY — the due date for this cycle
From — applying party
Company, contact name and role
To — paying party / contractor
As named in the subcontract
Period / cycle covered
e.g. valuation period 14 — to DD/MM/YYYY
Valuation reference
If a separate valuation number is used

2 · Payment dates (HGCRA)

Due date
As defined by the payment mechanism
Final date for payment
DD/MM/YYYY — typically 14-21 days from due date
Payment notice due by
Not later than 5 days after the due date

Under the HGCRA, the payer must issue a payment notice within 5 days of the due date stating the sum it considers due. If it does not, this application stands as the notified sum and becomes payable in full unless a valid pay-less notice is served before the final date for payment.

3 · Valuation of the works

Gross value of work done to date
£ — measured and completed work
Value of variations / change
£ — agreed and notified variations
Materials on/off site
£ — where the contract allows
Gross valuation total
£ sum of the above
Less retention
£ — state the percentage applied
Net valuation
£ gross less retention
Basis of valuation
How the figures were measured — reference the priced activity schedule, bill of quantities, or rates

4 · Sum applied for

Net valuation this period
£ from section 3
Less amounts previously certified / paid
£ cumulative to date
Net amount now applied for
£ — the notified sum (excl. VAT)
VAT
£ — if applicable
Total amount now due (incl. VAT)
£

5 · Retention

Retention percentage applied
% — typically 3-5%
Cumulative retention held
£ total withheld to date
Retention release due
DD/MM/YYYY — at completion / defects

6 · Supporting documents attached

Valuation / measure
Variation account
Materials invoices
Programme / progress record
Photographs
Other (list below)
Documents list
Itemise the documents that evidence this application

7 · Submitted by

Signed
Name and position
Date
DD/MM/YYYY

8 · Payer use — payment notice / pay-less reference

Payment notice issued — sum considered due agreed
Pay-less notice to follow — see separate notice
Sum the payer considers due
£ — if different from applied sum
Payment notice date
DD/MM/YYYY
Reference
Payer's internal reference

How to use this form

  1. 1

    Complete section 1 with a sequential application number and the dates for this valuation cycle.

  2. 2

    Record the HGCRA dates in section 2 — the due date, the final date for payment, and the date by which the payer must issue a payment notice.

  3. 3

    Build up the valuation in section 3 and carry the net figure into the sum applied for in section 4 — this is your notified sum.

  4. 4

    Keep the supporting documents listed in section 6 with the application; a well-evidenced application is harder to pay less against.

  5. 5

    Serve the application, keep proof of service, and diarise the payment-notice and pay-less deadlines — if the payer misses them, the notified sum becomes payable in full.

Get the printable PDF version

Enter your details and we'll email you a printable PDF of the Interim Payment Application Form — formatted for A4 and ready to use on site or in the office.

Choose your version

Protect your cash flow with LazyQS

Upload your subcontract and get a clause-level report on the payment mechanism, retention, set-off and pay-less rights — so you know your entitlements before you apply.

Review my subcontract free