Compensation Events (Clause 60.1)
NEC4 clause 60.1 lists 21 defined circumstances under which you are entitled to claim more time and money. Knowing each one — and notifying them promptly — protects your commercial position.
Overview of all compensation eventsClient instruction to change the Scope
Client does not allow access by a date in the Accepted Programme
Client does not provide something by a date in the Accepted Programme
Client gives instruction to stop or not to start work
Client or Others do not work within the conditions stated in the Scope
PM or Supervisor does not reply within the period required
PM gives instruction changing a decision previously communicated
PM changes an earlier decision on accepting a Contractor communication
Client notifies correction of a Defect that existed at Completion
Client notification to search for a Defect not caused by the Contractor
A test or inspection causes unnecessary delay
Physical conditions within the Site not weather
Weather measurements exceed stated limits
Event in Client's risk as stated in the Risk Register
PM certifies take over of part of the works before Completion date
Client does not provide materials, facilities, or samples as stated in Scope
PM notifies a correction to an assumption about a compensation event
A breach of contract by the Client
Event that stops Contractor completing by the planned Completion date
Additional compensation events stated in Contract Data
Client instructs the Contractor to prepare a revised programme
Main Options A–F
The main option defines the payment mechanism for the whole contract. Which option applies determines how you get paid, how risk is shared, and how cost is managed throughout the project.
Compare all main optionsX Clauses (Secondary Options)
X clauses are added to the main contract and each introduces a specific obligation or entitlement. Always check the Contract Data to confirm which X clauses are included — they vary significantly between projects.
Overview of all X clausesPrice adjustment for inflation
Changes in the law
Multiple currencies
Parent company guarantee
Sectional completion
Bonus for early Completion
Delay damages
Undertakings to the Client or Others
Transfer of rights
Information modelling (BIM)
Termination by the Client on notice
Multi-party collaboration
Performance bond
Not sure how a clause affects your current bid?
Upload your NEC contract to LazyQS and get a plain English review of the key risks, obligations, and compensation event opportunities — in minutes.