Plain English Explanation
X12 establishes a multi-party collaborative structure where two or more parties work together under a collaboration agreement coordinated with their individual NEC contracts. Under X12, a Core Group meets regularly to manage the project collectively, with decisions made on a collaborative basis.
X12 is associated with alliance contracting and integrated project delivery models. It is used on complex infrastructure, frameworks, and major programmes where multiple clients, contractors, and subcontractors need to be closely integrated. X12 promotes shared risk and reward across the collaborative entity.
X12 does not replace the individual NEC contracts — each party still has their own contract with the Client — but it adds an overarching collaborative governance layer.
Key Takeaway
X12 collaboration governance is resource-intensive — price the Core Group participation cost into your bid and ensure you understand what commercially sensitive information you will be required to share before committing.
What This Means for Subcontractors
If you are included in an X12 collaboration, you are part of the Core Group and have obligations to participate in collaborative governance. This can be resource-intensive. Understand what decisions the Core Group makes, what information you will need to share, and how the pain/gain mechanism operates across the alliance before pricing.
Common Risks & Disputes
- 1The collaborative governance structure being more time-consuming and costly than anticipated
- 2Decision-making within the Core Group being slow or contested, delaying the project
- 3Information sharing requirements revealing commercially sensitive data
- 4The pain/gain allocation across the X12 partners being disputed at completion
- 5Individual parties defaulting on their X12 obligations, undermining the collaborative structure
Sources
Related Clauses
Continue Learning
Category Overview
Back to X Clauses (Secondary Options)Adjacent Clauses
Not sure how X12 affects your current bid?
Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.
Upload Your Contract