Skip to main content

X Clauses (Secondary Options)

X clauses are secondary options that are bolted onto the main contract. Each one adds a specific obligation or right — from delay damages (X7) to BIM requirements (X10). Always check which X clauses are included in the Contract Data.

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

X clauses are secondary options — stand-alone provisions that are bolted onto whichever main option governs the contract. None of them apply automatically. Each X clause must be expressly included by reference in Contract Data Part 1, and only the X clauses listed there form part of the contract. This means two NEC contracts using the same main option can have completely different risk profiles depending on which X clauses are selected. Always read the Contract Data first — before you read anything else.

The X clauses cover a wide range of additional obligations and entitlements: X1 and X2 deal with inflation and legislative change risk; X4 and X13 with security requirements (parent company guarantees and performance bonds); X5, X6, and X7 with programme incentives and consequences (sectional completion, early completion bonuses, and delay damages); X8 through X10 with third-party obligations, intellectual property, and BIM; X11 and X12 with termination and collaborative contracting; and X13 with performance bonds.

For subcontractors, the most commercially significant X clauses are typically X7 (delay damages), X5 (sectional completion), X1 (inflation protection on long contracts), X13 (performance bond cost), and X4 (parent company guarantee requirements). The delay damages rate under X7 is often the largest single financial risk in a subcontract — a rate that is disproportionate to your package value can result in losses that exceed your contract sum. Always check the rate, check whether it has been passed down unmodified from the main contract, and ensure all CE notifications are made promptly to protect your programme.

Key Things to Know

  • X clauses only apply if they are expressly listed in Contract Data Part 1 — never assume an X clause applies; always check the Contract Data.
  • X7 (delay damages) is the most commercially dangerous X clause for subcontractors — always check the rate, verify it is proportionate to your package, and notify CEs promptly to protect your programme.
  • X5 (sectional completion) creates separate Completion dates, each with its own delay damage exposure — ensure your subcontract programme aligns with the defined sections.
  • X1 (inflation adjustment) should be in your subcontract on any project lasting more than 12 months — if it is in the main contract but not passed down, you carry the full inflation risk.
  • X13 (performance bond) and X4 (parent company guarantee) have cost and procurement implications — price the bond premium into your bid and allow time to arrange the security before contract execution.

Quick Reference

ClauseTitlePurposeWatch For
X1Price adjustment for inflationAdjusts contract price for published index movementsNot being passed down into subcontract on long projects
X2Changes in the lawCE for legislative changes after the base dateDistinguishing law changes from stricter enforcement
X3Multiple currenciesExchange rate protection for specified foreign currency itemsCurrency exposure on non-X3 items remaining with Contractor
X4Parent company guaranteePCG required from Contractor's parent companyArranging a suitable guarantor if no appropriate parent exists
X5Sectional completionSeparate Completion dates per section with individual delay damagesMultiple simultaneous delay damage exposures
X6Bonus for early CompletionFinancial incentive for completing before the Completion dateBonus not flowing down to subcontractors who enabled early finish
X7Delay damagesLiquidated damages for late CompletionRate being disproportionate to subcontract value
X8Undertakings to Client or OthersStructured obligations to named third partiesObligations to funders or tenants creating direct third-party liability
X9Transfer of rightsAssignment or licensing of intellectual property to the ClientPI insurance restrictions on scope of rights transferred
X10Information modelling (BIM)BIM compliance requirements as a contractual obligationBIM capability gaps and unpriced BIM deliverables
X11Termination by Client on noticeClient's right to terminate for convenienceTermination fee adequacy versus lost profit on remaining works
X12Multi-party collaborationAlliance/collaborative governance structureResource burden of Core Group participation
X13Performance bondCapped surety bond as security for Contractor performanceBond cost not being priced into bid; on-demand bond risk

Frequently Asked Questions

Which NEC X clauses are most important for subcontractors?

X7 (delay damages) is the most commercially significant — check the rate and ensure it is proportionate to your package value. X5 (sectional completion), X1 (inflation adjustment), X13 (performance bond), and X4 (parent company guarantee) are also commonly relevant.

Do all X clauses apply to every NEC contract?

No. X clauses only apply if they are expressly listed in Contract Data Part 1. Two NEC contracts using the same main option can have completely different X clause selections. Always check the Contract Data before assuming any X clause applies.

What is NEC clause X7 (delay damages)?

X7 provides for liquidated damages payable by the Contractor if Completion is later than the Completion Date. The rate is stated in Contract Data Part 1. For subcontractors, a disproportionate X7 rate passed down from the main contract is one of the largest financial risks in any NEC subcontract.

X1

Price adjustment for inflation

X1 provides for the contract price to be adjusted upward (or downward) to reflect changes in the price level of labour, materials, and plant between the base date and the date of work. It uses a formu...

X2

Changes in the law

X2 provides for a compensation event if there is a change in the law of the country in which the site is located after the base date of the contract. If new legislation, regulations, or statutory requ...

X3

Multiple currencies

X3 allows for certain defined items in the contract to be paid in currencies other than the currency of the main contract. This is relevant for international projects or where key components are purch...

X4

Parent company guarantee

X4 requires the Contractor to provide a parent company guarantee (PCG) from its parent or holding company. A PCG is an undertaking by the parent company to meet the Contractor's obligations if the Con...

X5

Sectional completion

X5 allows the contract to be divided into sections, each with its own Completion date, defects correction period, and associated delay damages. Without X5, the NEC contract has a single Completion dat...

X6

Bonus for early Completion

X6 provides a financial incentive for the Contractor to complete the works (or sections under X5) earlier than the Completion date. If the PM certifies Completion before the Completion date, the Contr...

X7

Delay damages

X7 provides for delay damages (liquidated damages) to be levied against the Contractor if they fail to complete the works by the Completion date. The rate of delay damages is stated in the Contract Da...

X8

Undertakings to the Client or Others

X8 (introduced in NEC4) requires the Contractor to provide undertakings to the Client and to third parties (Others) as stated in the Contract Data. These undertakings are direct obligations that sit a...

X9

Transfer of rights

X9 addresses the transfer of intellectual property rights. Under X9, the Contractor assigns or licenses the Client to use documents, designs, software, and other materials created in connection with t...

X10

Information modelling (BIM)

X10 sets out the requirements for information modelling — principally Building Information Modelling (BIM). The Contractor is required to comply with an Information Model and Information Execution Pla...

X11

Termination by the Client on notice

X11 gives the Client the right to terminate the contract at any time by giving notice to the Contractor, without needing to demonstrate fault on the Contractor's part. This is a 'termination for conve...

X12

Multi-party collaboration

X12 establishes a multi-party collaborative structure where two or more parties work together under a collaboration agreement coordinated with their individual NEC contracts. Under X12, a Core Group m...

X13

Performance bond

X13 requires the Contractor to provide a performance bond — a bond from a surety (typically an insurer or bank) that will pay out to the Client if the Contractor fails to perform their obligations. Th...

Not sure how these clauses affect your current bid?

Upload your NEC contract to LazyQS and get a plain English review of the key risks, obligations, and compensation event opportunities — in minutes.

Upload Your Contract