60.1(11)

A test or inspection causes unnecessary delay

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

Plain English Explanation

Under NEC, tests and inspections are required by the contract (set out in the Scope). If a test or inspection is carried out by the Supervisor (Client's representative for quality) and the delay to the Contractor caused by that test or inspection is greater than what was allowed for in the Accepted Programme, the excess delay is a CE.

The key word is 'unnecessary' — meaning delay beyond what the contract anticipated for that test or inspection. If a test simply takes longer than planned because of the Supervisor's thoroughness, or because they fail to attend on time, the excess time is recoverable as a CE.

This CE is particularly relevant on projects with extensive quality hold points, factory acceptance testing, or complex commissioning sequences.

Key Takeaway

Programme the allowance for each test and inspection explicitly in your Accepted Programme — only the excess beyond that allowance is recoverable, so a clear baseline is essential.

What This Means for Subcontractors

Subcontractors on heavily quality-managed packages (mechanical, electrical, structural steel, cladding) should programme sufficient time for tests and inspections. If the Supervisor causes hold-up beyond the programmed allowance — for example by failing to attend or requiring repeated inspections — keep records and notify a CE for the excess delay.

Common Risks & Disputes

  • 1Not having a clear baseline in the Accepted Programme for how long each test or inspection should take
  • 2The Supervisor attending late or requiring re-tests without clear justification
  • 3Failing to record the duration of each test and inspection against the programmed allowance
  • 4The PM arguing the delay was caused by the Contractor's own failure to prepare adequately for the test
  • 5Tests delayed by third-party laboratories or equipment failures — these may not be attributable to the Supervisor

Sources

  1. NEC4 ECC Clause 60.1(11)NEC4 ECC
  2. RICS Guidance Note: Compensation Events under NEC ContractsRICS
  3. ICE Guidance: Tests, Inspections and Hold Points Under NEC4ICE

Related Clauses

Continue Learning

Not sure how 60.1(11) affects your current bid?

Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.

Upload Your Contract