Skip to main content
60.1(6)

PM or Supervisor does not reply within the period required

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

Plain English Explanation

Under NEC, the contract sets specific time periods for the PM and Supervisor to respond to communications — typically two weeks unless a different period is stated in Contract Data. If the PM or Supervisor fails to reply within that period (for example, to an Early Warning, a request for an instruction, or a submission), this triggers a compensation event.

This CE reinforces one of NEC's core principles: timely communication and decision-making. If either party causes delay through inaction, the contract provides a remedy. The CE applies to things like: approval of designs or materials, decisions on Defects, responses to quotations, and acceptance of programmes.

In practice, this CE is frequently available but rarely formally notified — contractors often absorb the delay and move on. Tracking response times carefully can unlock legitimate entitlements.

Key Takeaway

Log every submission with its submission date and the contractual reply deadline — a systematic log turns an overlooked CE into a straightforward entitlement.

What This Means for Subcontractors

Under a subcontract, the main contractor takes on the PM role. If the main contractor is slow to respond to submittals, design queries, or requests for approval, this CE may be available. Keep a log of all submissions with submission dates and required response dates. Chase formally rather than informally — an email log is your evidence.

Common Risks & Disputes

  • 1Not tracking submission and response dates systematically, making it hard to demonstrate a breach
  • 2The PM arguing they did respond, or that the communication was incomplete so the period did not start
  • 3Informal responses (verbal or email) being used to argue that a substantive reply was given
  • 4Not being aware of what the contractual reply period is in your specific contract
  • 5Accepting late responses without formally notifying a CE, which may bar your entitlement

Sources

  1. NEC4 ECC Clause 60.1(6)NEC4 ECC
  2. RICS Guidance Note: Compensation Events under NEC ContractsRICS
  3. Fenwick Elliott: PM Reply Periods and CE Entitlement Under NEC4Fenwick Elliott

Related Clauses

Continue Learning

Not sure how 60.1(6) affects your current bid?

Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.

Upload Your Contract