Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19
Compensation events (CEs) are the mechanism by which NEC4 manages change and risk during a construction project. Unlike traditional variation orders under JCT contracts, NEC CEs are not just about scope changes — they cover any defined event that causes the Contractor to incur more cost or take more time than was anticipated at the Contract Date. Clause 60.1 lists 21 such events, ranging from PM instructions to change the Scope (60.1(1)) through to unforeseen ground conditions (60.1(12)) and weather exceeding historical thresholds (60.1(13)).
For subcontractors, the CE mechanism is both a protection and a discipline. It protects you by providing a contractual route to recover additional time and cost whenever a defined event occurs. The discipline is the notification regime: under NEC4 you must notify the PM of a CE within 8 weeks of becoming aware of it. 'Becoming aware' is not the same as the event occurring — you are expected to identify and notify events promptly. Fail to notify in time and you lose your entitlement, regardless of the merits of your claim. This time-bar is the most commercially significant procedural requirement in NEC contracting.
Contemporaneous records are the foundation of every CE claim. The NEC CE process requires you to price the impact on Defined Cost and the Accepted Programme. Without site diaries, labour allocation sheets, plant records, and programme updates, you cannot substantiate either element. Many subcontractors win the right to a CE in principle but then fail to recover fair compensation because they cannot demonstrate actual cost. Treat every potential CE as a claim from the moment you become aware of it — don't wait until the event is over to start assembling your records.