Skip to main content

Compensation Events

NEC4 clause 60.1 lists 21 compensation events — the defined circumstances under which a contractor (or subcontractor) is entitled to claim more time and/or money. Understanding each one is critical to protecting your commercial position.

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

Compensation events (CEs) are the mechanism by which NEC4 manages change and risk during a construction project. Unlike traditional variation orders under JCT contracts, NEC CEs are not just about scope changes — they cover any defined event that causes the Contractor to incur more cost or take more time than was anticipated at the Contract Date. Clause 60.1 lists 21 such events, ranging from PM instructions to change the Scope (60.1(1)) through to unforeseen ground conditions (60.1(12)) and weather exceeding historical thresholds (60.1(13)).

For subcontractors, the CE mechanism is both a protection and a discipline. It protects you by providing a contractual route to recover additional time and cost whenever a defined event occurs. The discipline is the notification regime: under NEC4 you must notify the PM of a CE within 8 weeks of becoming aware of it. 'Becoming aware' is not the same as the event occurring — you are expected to identify and notify events promptly. Fail to notify in time and you lose your entitlement, regardless of the merits of your claim. This time-bar is the most commercially significant procedural requirement in NEC contracting.

Contemporaneous records are the foundation of every CE claim. The NEC CE process requires you to price the impact on Defined Cost and the Accepted Programme. Without site diaries, labour allocation sheets, plant records, and programme updates, you cannot substantiate either element. Many subcontractors win the right to a CE in principle but then fail to recover fair compensation because they cannot demonstrate actual cost. Treat every potential CE as a claim from the moment you become aware of it — don't wait until the event is over to start assembling your records.

Key Things to Know

  • Always notify within 8 weeks of becoming aware of a CE — 'aware' means when you first had knowledge, not when the event concluded or when you quantified the impact.
  • A verbal instruction from the PM still triggers a CE under 60.1(1) — you do not need a formal variation order, just an instruction that changes the Scope.
  • The CE mechanism covers far more than scope changes: access failures, late information, PM response delays, unforeseen ground conditions, and weather all have their own CE triggers.
  • Keep contemporaneous records from day one — site diaries, labour records, plant allocation, and programme updates are the foundation of every CE assessment.
  • Notify early and price later — submitting a CE notification preserves your entitlement even if you cannot yet quantify the full impact; you have time to assess and submit your quotation separately.

Quick Reference

ClauseTitleTriggerFrequency
60.1(1)Change to ScopePM instruction altering the defined ScopeCommon
60.1(2)Access not givenClient fails to give site access by programmed dateCommon
60.1(3)Client does not provide somethingClient fails to provide items by programmed dateModerate
60.1(4)Stop/don't start instructionPM instructs suspension of all or part of the worksModerate
60.1(5)Others breach Scope conditionsClient or Others fail to work within stated conditionsModerate
60.1(6)PM/Supervisor late replyPM or Supervisor fails to respond within contractual periodCommon
60.1(7)Changed PM decisionPM reverses a decision previously communicatedModerate
60.1(8)Withdrawal of acceptancePM withdraws acceptance of a Contractor submissionRare
60.1(9)Post-Completion Defect correctionClient notifies pre-Completion Defect after Defects DateRare
60.1(10)Search for Defect not caused by ContractorPM instructs search; no Contractor-caused Defect foundModerate
60.1(11)Test or inspection causes unnecessary delayTest or inspection exceeds programmed allowanceModerate
60.1(12)Unforeseen physical conditionsGround or site conditions beyond experienced contractor's allowanceCommon
60.1(13)Exceptional weatherWeather measurements exceed contractual thresholdsModerate
60.1(14)Client risk event in Risk RegisterEvent listed as Client risk in Risk Register materialisesModerate
60.1(15)Early take-overPM certifies take-over of part of works before Completion dateRare
60.1(16)Client does not provide free-issue itemsClient fails to provide materials/facilities stated in ScopeModerate
60.1(17)Correction of CE assumptionPM notifies that an assumption used in CE quotation was wrongModerate
60.1(18)Client breach of contractClient breaches a contractual obligation not covered by other CEsRare
60.1(19)Force majeure eventEvent beyond Contractor's control stops completion by planned dateRare
60.1(20)Additional CEs in Contract DataBespoke CE events added by parties in Contract Data Part 1Moderate
60.1(21)Instruction to prepare revised programmePM instructs a programme revision beyond routine contractual updatesRare

Frequently Asked Questions

What is the 8-week time bar for NEC compensation events?

Under NEC4, the Contractor must notify a compensation event within 8 weeks of becoming aware of it. If notification is late, the PM can reject it and the Contractor loses entitlement to additional time and money — regardless of the merits.

Can a subcontractor claim a compensation event under NEC?

Yes. NEC subcontracts contain equivalent compensation event clauses. The Contractor takes on the Client role, and the subcontractor must notify CEs to the Contractor within the required time limits.

What records do I need to support a compensation event claim?

You need contemporaneous records including site diaries, labour allocation sheets, plant records, photographic evidence, and programme updates. The NEC CE assessment is based on Defined Cost and the effect on the Accepted Programme.

60.1(1)

Client instruction to change the Scope

This is the most commonly used compensation event. It arises when the Project Manager (PM) gives an instruction that changes the Scope — the document that defines what you must do. The Scope includes ...

60.1(2)

Client does not allow access by a date in the Accepted Programme

This CE arises when the Client fails to give you access to the Site (or a part of it) by the date shown on the Accepted Programme. Access dates are not just the start date — they apply to each area or...

60.1(3)

Client does not provide something by a date in the Accepted Programme

Similar to 60.1(2), this CE covers situations where the Client is supposed to provide something — materials, equipment, information, or a free-issue item — by a date in the Accepted Programme, but fai...

60.1(4)

Client gives instruction to stop or not to start work

This CE is triggered when the PM instructs the contractor to stop work that is already underway, or not to start an activity that was planned. This is sometimes called a 'suspension' or 'stop notice'....

60.1(5)

Client or Others do not work within the conditions stated in the Scope

This CE covers situations where the Client, or parties described as 'Others' in the contract (e.g. other contractors appointed directly by the Client), fail to work within the conditions set out in th...

60.1(6)

PM or Supervisor does not reply within the period required

Under NEC, the contract sets specific time periods for the PM and Supervisor to respond to communications — typically two weeks unless a different period is stated in Contract Data. If the PM or Super...

60.1(7)

PM gives instruction changing a decision previously communicated

This CE arises when the PM changes a decision they have already communicated to you. If you have acted in reliance on the PM's earlier decision and they then change it, you are entitled to a CE for th...

60.1(8)

PM changes an earlier decision on accepting a Contractor communication

This CE applies where the PM has previously accepted a Contractor communication — such as a design submission, a programme, or a method statement — and subsequently notifies the Contractor that they a...

60.1(9)

Client notifies correction of a Defect that existed at Completion

This CE arises in a specific post-Completion scenario. Under NEC, at the Defects Date (the end of the defect correction period), if the Client has not notified a Defect that existed at Completion, the...

60.1(10)

Client notification to search for a Defect not caused by the Contractor

Under NEC, the PM can instruct the Contractor to search for a Defect — opening up completed works, testing, or investigating. If the search reveals a Defect that was not caused by the Contractor (e.g....

60.1(11)

A test or inspection causes unnecessary delay

Under NEC, tests and inspections are required by the contract (set out in the Scope). If a test or inspection is carried out by the Supervisor (Client's representative for quality) and the delay to th...

60.1(12)

Physical conditions within the Site not weather

This CE arises when the Contractor encounters physical conditions within the Site — things encountered in or on the ground — that an experienced contractor would have judged, at the Contract Date, to ...

60.1(13)

Weather measurements exceed stated limits

This CE applies where weather conditions at the Site are recorded as more severe than the weather measurements stated in the Contract Data (or, if not stated, as would have occurred less than once in ...

60.1(14)

Event in Client's risk as stated in the Risk Register

Under NEC4, the contract includes a Risk Register — a live document maintained by the PM that records identified risks and who owns them. Risks can be allocated to the Client, the Contractor, or share...

60.1(15)

PM certifies take over of part of the works before Completion date

This CE arises when the PM certifies that the Client has taken over a part of the works before the Completion date. Under NEC4, if the Client starts using a section of the works before Completion (and...

60.1(16)

Client does not provide materials, facilities, or samples as stated in Scope

This CE covers the situation where the Scope states that the Client will provide certain materials, facilities, samples, or equipment for the Contractor's use, and the Client fails to provide them. Th...

60.1(17)

PM notifies a correction to an assumption about a compensation event

When the PM assesses a compensation event that involves an uncertain future event, they can state assumptions about that event and instruct you to quote on that basis. If those assumptions later prove...

60.1(18)

A breach of contract by the Client

This CE is a broad catch-all that covers any breach of contract by the Client that is not already covered by one of the other compensation events. Under NEC4, if the Client breaches an obligation and ...

60.1(19)

Event that stops Contractor completing by the planned Completion date

This CE applies where an event occurs that stops the Contractor completing the works by the planned Completion date — and that event is not one of the other listed CEs and is not the Contractor's faul...

60.1(20)

Additional compensation events stated in Contract Data

NEC contracts allow the parties to add additional compensation events to the standard list through the Contract Data. These are bespoke CEs agreed at tender stage that are specific to the project or t...

60.1(21)

Client instructs the Contractor to prepare a revised programme

This CE applies where the PM instructs the Contractor to prepare a revised programme — meaning a new programme beyond those that are required under the contract in the normal course of events. NEC con...

Not sure how these clauses affect your current bid?

Upload your NEC contract to LazyQS and get a plain English review of the key risks, obligations, and compensation event opportunities — in minutes.

Upload Your Contract