Plain English Explanation
Similar to 60.1(2), this CE covers situations where the Client is supposed to provide something — materials, equipment, information, or a free-issue item — by a date in the Accepted Programme, but fails to do so. The Client's obligations to provide things are set out in the Scope and Contract Data.
Common examples include: Client-supplied plant or equipment, information packages (surveys, geotechnical reports), utility connections, design information, or interfaces with Client-run systems. If any of these are late, this CE is triggered.
This CE reinforces the collaborative nature of NEC — both parties have obligations, and a failure by either side is dealt with through the compensation event mechanism rather than disputes.
Key Takeaway
Include every item the Client or main contractor must provide in your Accepted Programme with a specific required date — without it in the programme, the CE trigger does not exist.
What This Means for Subcontractors
Under a subcontract, the Contractor takes on the Client's role. If the main contractor fails to provide free-issue materials, design drawings, or plant by the dates shown in your programme, you should notify a CE. Ensure your subcontract programme is detailed enough to show the dates by which you need each deliverable from the main contractor.
Common Risks & Disputes
- 1Client obligations not being listed in the Scope with clear delivery dates
- 2The PM arguing that the item was provided 'substantially' on time or that the delay was immaterial
- 3Failure to record the impact of late information on your works — programme disruption is often more significant than direct delay
- 4Relying on informal chasing rather than formal CE notifications when information is late
- 5Inadequate detail in the Accepted Programme — the dates must be expressly shown to trigger entitlement
Sources
Related Clauses
Client does not allow access by a date in the Accepted Programme
Access failure — parallel Client obligation to give site access
Client does not provide materials, facilities, or samples as stated in Scope
Failure to provide free-issue materials stated in the Scope
Client or Others do not work within the conditions stated in the Scope
Others breaching conditions that also covers Client failures
Continue Learning
Not sure how 60.1(3) affects your current bid?
Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.
Upload Your Contract