Skip to main content
60.1(4)

Client gives instruction to stop or not to start work

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

Plain English Explanation

This CE is triggered when the PM instructs the contractor to stop work that is already underway, or not to start an activity that was planned. This is sometimes called a 'suspension' or 'stop notice'. The instruction may apply to all of the works or just a specific section.

Reasons for this instruction can include: Client funding issues, planning hold-ups, health and safety concerns, design reviews, interface problems with other contractors, or simply a change in Client priorities. Whatever the reason, if the PM issues such an instruction, you are entitled to a CE for both time and additional cost.

Unlike termination (which is handled elsewhere in the contract), a stop/don't start instruction assumes the works will eventually resume. You should still price and programme the impact of stopping and restarting.

Key Takeaway

A stop instruction is a CE the moment it is issued — price demobilisation, standing time, and remobilisation costs in your CE quotation, not just the direct delay.

What This Means for Subcontractors

Suspension instructions passed down from the main contractor to subcontractors are often the result of a Client instruction at the top of the chain. Ensure your subcontract has a clear suspension mechanism and that the main contractor's obligation to pass on the Client-level CE relief is preserved. Prolonged suspension can also trigger termination rights — check your contract's thresholds.

Common Risks & Disputes

  • 1Accepting a stop instruction without notifying a CE, particularly if the reason is presented as 'temporary'
  • 2Demobilisation and remobilisation costs being overlooked — these can be significant and must be included in your CE quotation
  • 3Prolonged suspension eroding subcontractor leverage and cashflow without formal relief
  • 4The PM arguing that the stop was caused by your own default (e.g. a Defect) which is excluded
  • 5Failure to price correctly for the cost of maintaining site presence during a stop period

Sources

  1. NEC4 ECC Clause 60.1(4)NEC4 ECC
  2. RICS Guidance Note: Compensation Events under NEC ContractsRICS
  3. ICE Guidance: Suspension of Works and CE Entitlement Under NECICE
  4. Fenwick Elliott: Stop and Don't Start Instructions Under NEC4Fenwick Elliott

Related Clauses

Continue Learning

Not sure how 60.1(4) affects your current bid?

Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.

Upload Your Contract