Plain English Explanation
This CE applies where the PM instructs the Contractor to prepare a revised programme — meaning a new programme beyond those that are required under the contract in the normal course of events. NEC contracts require programmes to be revised at specified intervals or in response to CE notifications, and the cost of those routine revisions is part of normal overhead.
However, if the PM instructs a programme revision over and above what would normally be required — for example, to support a dispute, to investigate a complex delay, or to model multiple scenarios — the cost of preparing that additional programme is recoverable as a CE.
Programme preparation and maintenance is a significant cost on complex NEC projects, and this CE protects the Contractor from being directed to carry out extensive additional programming work for free.
Key Takeaway
Track and record the time your programming team spends on every revision — if the PM instructs additional revisions beyond the routine contractual requirement, that cost is recoverable as a CE.
What This Means for Subcontractors
Subcontractors are sometimes required to submit detailed programmes as part of the main contractor's reporting obligations. If the main contractor directs you to prepare additional or revised programmes beyond what your subcontract requires, you may have an entitlement under the equivalent subcontract CE provision. Establish clearly at the outset what programme submissions are required under your subcontract.
Common Risks & Disputes
- 1Distinguishing between routine programme revisions (which are part of the contract) and additional revisions that trigger a CE
- 2The PM arguing the revision was a normal update rather than an additional instruction
- 3Not recording the time spent preparing the revised programme, making it hard to claim the cost
- 4Failing to notify a CE for the additional programming work, then absorbing the cost as overhead
- 5Revised programmes requested verbally being treated as part of normal collaboration rather than a PM instruction
Sources
Related Clauses
Continue Learning
Category Overview
Back to Compensation EventsAdjacent Clauses
Not sure how 60.1(21) affects your current bid?
Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.
Upload Your Contract