Skip to main content
60.1(20)

Additional compensation events stated in Contract Data

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

Plain English Explanation

NEC contracts allow the parties to add additional compensation events to the standard list through the Contract Data. These are bespoke CEs agreed at tender stage that are specific to the project or the Client's requirements. They supplement the standard 60.1(1) to 60.1(21) list.

Projects sometimes use this provision to include events such as: statutory undertaker delays, planning condition restrictions, specific interface risks, or other project-specific uncertainties. These additional CEs are as enforceable as the standard ones and should be treated accordingly.

Always review Contract Data Part 1 carefully at tender stage to identify any additional CEs. Price and programme for them, and ensure they are passed down appropriately in your subcontract.

Key Takeaway

Read Contract Data Part 1 line by line at tender — an additional CE you miss during bid review cannot be raised after the event, but one you identify can be negotiated, priced, and passed down into your subcontract.

What This Means for Subcontractors

Subcontractors should always check whether additional CEs have been included in the Contract Data. These may include events that specifically affect your package. Equally, push for additional CEs to be included in the subcontract for risks that are within the main contractor's control — this gives you clear entitlement if those risks materialise.

Common Risks & Disputes

  • 1Contract Data not being reviewed thoroughly at tender stage, so additional CEs are missed
  • 2Additional CEs being poorly drafted, making it difficult to determine when the triggering event has occurred
  • 3Additional CEs not being passed down into subcontracts, leaving subcontractors without protection for project-specific risks
  • 4The PM arguing an additional CE has not been triggered because the drafting is ambiguous
  • 5Relying on the standard list without checking for project-specific additions

Sources

  1. NEC4 ECC Clause 60.1(20)NEC4 ECC
  2. RICS Guidance Note: Compensation Events under NEC ContractsRICS
  3. ICE Guidance: Project-Specific CE Provisions and Contract Data Under NEC4ICE

Related Clauses

Continue Learning

Not sure how 60.1(20) affects your current bid?

Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.

Upload Your Contract