Plain English Explanation
Option B is a re-measurable contract — the work is priced against a Bill of Quantities (BoQ) with rates and prices, and the contract sum is adjusted based on the actual quantities of work executed. If you do more work than the BoQ anticipated, you are paid more; if you do less, you are paid less.
The BoQ sets out items of work with estimated quantities and your agreed rates. At each interim payment, actual quantities are measured and valued at those rates. This gives the Client less price certainty than Option A but provides a more accurate reflection of actual work done. Option B is common on civils and infrastructure projects where quantities cannot be precisely defined at tender.
Option B still allows for compensation events — scope changes, Client-caused delays, and the other 60.1 events are dealt with through the CE mechanism.
Key Takeaway
Agree and sign off interim measurements regularly throughout the project — leaving re-measurement to the end creates end-of-project disputes that are expensive and slow to resolve.
What This Means for Subcontractors
Under Option B, your payment tracks actual work done at agreed rates. Cashflow is generally better than Option A because you are not waiting for an activity to be complete. However, rate disputes can arise — particularly where the character of the work differs from what was anticipated when the BoQ was priced. Monitor measurements carefully and agree them regularly to avoid end-of-project disputes.
Common Risks & Disputes
- 1Quantity disputes at interim valuation, particularly for complex or hard-to-measure items
- 2Rates becoming inadequate if the character of the work changes substantially (different ground conditions, different access, etc.)
- 3BoQ errors at tender — incorrect quantities that distort the contract sum
- 4Omissions from the BoQ not being identified at tender and then becoming contentious at completion
- 5The re-measurement process falling behind programme, leading to delayed payment
Sources
Related Clauses
Priced contract with Activity Schedule
Activity Schedule alternative — fixed price, different cashflow profile
Target contract with Activity Schedule
Target cost with Activity Schedule — adds pain/gain on top of re-measurement
Target contract with Bill of Quantities
Target cost with BoQ — closest structural equivalent to Option B
Continue Learning
Category Overview
Back to Main Options (A–F)Not sure how Option B affects your current bid?
Upload your NEC contract to LazyQS and get a clause-by-clause risk report with plain English explanations and recommended actions.
Upload Your Contract