Skip to main content

Main Options (A–F)

NEC contracts come in six main options that define the payment mechanism. Which option applies determines how you get paid, how risk is shared, and how cost is managed. The wrong option for your business model can severely impact cashflow.

Reviewed by LazyQS Editorial·Last reviewed: 2026-02-19

The main option is the most fundamental commercial choice in an NEC contract. It defines how the Contractor is paid, who bears the financial risk of cost overruns, and how the contract sum is established and adjusted. There are six main options — A through F — and which one applies is stated in Contract Data Part 1. Subcontractors often receive subcontracts on whichever option the main contractor considers appropriate for the package, which may differ from the main contract option above.

Options A and B are priced contracts where the Contractor bears cost risk — you price the work and are paid that price regardless of actual cost. Option A uses an Activity Schedule (lump sum activities) and Option B uses a Bill of Quantities (re-measurable). These options are the most common in the UK construction market. Options C and D are target cost contracts — the Contractor is paid actual Defined Cost plus a Fee, and any saving or overrun against the target is shared between the parties. Option E is a pure cost reimbursable contract with no target, and Option F is a management contract where the Contractor manages packages but does not self-deliver the physical works.

For subcontractors, the most important question is: what is the payment mechanism and who bears cost risk? Under Options A and B, your price is largely fixed (subject to CEs). Under Options C and D, you may need to provide open-book cost data and participate in a pain/gain calculation. Under Option E, all your costs must be demonstrable and auditable. Understanding which option applies — and what obligations flow to you — is essential before you submit a price.

Key Things to Know

  • Always identify the main option before pricing — it determines whether you bear cost risk (Options A/B), share it (Options C/D), or pass it to the Client (Option E).
  • Under Option A, you are paid when activities are complete — price your Activity Schedule in small enough increments to maintain monthly cashflow.
  • Under Options C and D, you may be required to provide open-book cost records; factor the administrative resource required into your pricing.
  • The CE mechanism applies equally across all options — scope changes, access failures, and other defined events are recoverable regardless of which option governs payment.
  • Under Option F, the management contractor has limited incentive to absorb CE claims on your behalf — push for your CE entitlements directly and promptly.

Quick Reference

OptionPayment MechanismRisk AllocationBest For
Option ALump sum by Activity ScheduleContractor bears cost overrun riskWell-defined scope, building/fit-out
Option BRe-measurement by Bill of QuantitiesContractor bears rate risk; Client bears quantity riskCivil works, uncertain quantities
Option CDefined Cost + Fee; target with Activity SchedulePain/gain shared per Contract Data splitComplex projects, incentivised delivery
Option DDefined Cost + Fee; target with Bill of QuantitiesPain/gain shared; dual-track measurement and cost accountingLarge infrastructure, framework programmes
Option EDefined Cost + Fee; no targetClient bears all cost riskEmergency works, early start, high uncertainty
Option FManagement fee + pass-through of subcontract costsClient bears subcontract cost risk; Contractor bears management riskMajor programmes, professional management

Frequently Asked Questions

Which NEC main option is best for subcontractors?

Options A and B are the most common for subcontracts. Option A (Activity Schedule) gives price certainty but requires careful activity breakdown for cashflow. Option B (Bill of Quantities) allows re-measurement but exposes you to rate risk. The best option depends on scope certainty and your risk appetite.

What is the difference between NEC Option A and Option B?

Option A pays a lump sum per completed activity (Activity Schedule). Option B pays re-measured quantities at tendered rates (Bill of Quantities). Under Option A, the Contractor bears both rate and quantity risk. Under Option B, the Client bears quantity risk but the Contractor still bears rate risk.

Do compensation events apply to all NEC main options?

Yes. The compensation event mechanism under clause 60.1 applies equally across all six main options (A–F). Scope changes, access failures, and other defined events are recoverable regardless of which payment mechanism governs the contract.

Not sure how these clauses affect your current bid?

Upload your NEC contract to LazyQS and get a plain English review of the key risks, obligations, and compensation event opportunities — in minutes.

Upload Your Contract